Mexico Cerro de Oro Hydroelectric |
Problem-Solving
|
Milestones and OA Actions |
Date
|
Remarks
|
|
Request received by OA
|
11-30-2010
|
Incoming Request
|
|
Request acknowledged by OA
|
12-06-2010
|
|
|
Eligibility of request determined
|
12-20-2010
|
Requests from Santa Ursula, Paso Canoa, and Cerro de Oro communities deemed eligible
|
|
Assessment conducted
|
01-15-2011
|
Assessment visit determined that both parties willing to engage in problem-solving process
|
|
Problem-solving initiated
|
03-11-2011
|
March 11 Agreement English | Spanish
May 5 Agreement English | Spanish
July 20 Agreement English | Spanish
|
|
Problem-solving terminated
|
11-14-2011
|
Initial Problem-Solving Report English| Spanish
Final Problem Solving Report English| Spanish
|
|
Monitoring initiated
|
|
Since the parties did not reach final agreement, no monitoring was initiated
|
Compliance Review
|
Milestones and OA Actions
|
Date
|
Remarks
|
|
Request received by OA
|
11-30-2010
|
Incoming Request
|
|
Request acknowledged by OA
|
12-06-2010
|
|
|
Eligibility of request determined
|
12-20-2010
|
Requests from Santa Ursula, Paso Canoa, and Cerro de Oro communities deemed eligible
|
|
Assessment conducted
|
|
A separate assessment for compliance review was not necessary
|
|
Compliance review initiated
|
01-12-2011
|
|
|
Compliance review completed and parties notified
|
01-04-2012
|
Compliance Review English | Spanish
|
|
Management response issued
|
10-12-2012
|
OPIC Management Response
|
|
Monitoring initiated
|
|
Since the compliance review did not result in an audit, monitoring was not initiated.
|
|