PS 1/2008 - Bolivia Coeur d'Alene Mines |
|
Steps and Milestones
|
Date
|
Remarks
|
|
1. Filing of request |
24 April 08 |
|
|
2. Acknowledge request |
15 May 08 |
|
|
3. Determine eligibility of request |
30 May 08 |
Problem-solving request accepted. |
|
4. Preliminary investigation |
24 February 09 |
Parties did not agree to participate |
|
5. Problem-solving consultation |
|
|
|
6. Report to President & CEO |
|
|
|
7. Notify parties and make conclusions public |
|
|
|
8. Post-report monitoring |
|
|
|