Public Registry

CR 1/2006 - Baku - Tbilisi - Ceyhan Pipeline

Steps and Milestones
Date
Remarks
1. Filing of request 18 May 06 BTC Pipeline Project Complaint
2. Register and acknowledge request 22 May 06  
3. Determine eligibility of request 22 May 06  
4. Examine compliance 1 June 06 - Dec 06  
5. Draft compliance review report 14 Dec 06  
6. Final report to President & CEO 29 Jan 07  
7. Notify parties and make conclusions public 12 Feb 07 Compliance Review of OPIC's Environmental Due Diligence & Monitoring of the BTC Oil Pipeline Project
8. Post-report monitoring  Oct 10 BTC Monitoring Report - OA - October 2010